(1) These Guidelines have been developed to support delegates in executing delegated authorities. This document should be read in conjunction with the Delegation of Authority Framework and its associated higher level documents. (2) The Delegation of Authority Framework should be referenced for context specific definitions. (3) Nothing in this guideline authorises a delegate to do anything which is, or is likely to be, a breach of an approved code of conduct of the (4) Any matter considered to be a delegation of authority that is not included in the Delegation Schedules should be referred to the most senior position within the (5) A delegate should consider the wider impact of a potential decision before making a commitment, including but not limited to: (6) A financial limit to a delegation of authority for incurring expenditure: (7) Nothing in the below example should be taken to interpret an actual Head Agreement or Sub-Agreement, and reference should always be made to the current Schedule, available in the Delegations Register. (8) Where a delegated authority exists to approve a contract for a funding commitment; and a separate delegated authority exists to authorise expenditure related to that contract, separate delegates may exercise each individual delegation of authority providing: (9) To determine who can approve a contract variation, the limits of the relevant delegated authority should be applied to the sum of the original contract cost, plus the cost of all variations. This applies to all types of contracts, regardless of the relevant authority. (For example, this applies equally to contracts for supply of capital items, contractor services, agency hire staff, operational supplies, etc). (10) Where the signature of a delegate is required, the Authorised Person must write the words "For and on behalf of (the Role title) as an Authorised Person", so it is clear that the person is acting under the authority of the Delegate.Delegation of Authority Guidelines
Section 1 - Purpose
Section 2 - Guidelines
General
Due Diligence
Financial Transaction Limits
Contracts and Agreements
Collaborative Agreements – Head and Sub Agreements
Table 1 – Example of Collaborative Head and Sub Agreements
Example
Correct Delegate and Limit
The Director, Research Grants can execute the sub-agreement under delegation F1. The Director, Research Grants has an unlimited authority for ARC agreements.
The Deputy Vice-Chancellor (Research and Innovation) must execute the Head Agreement and the Sub-Agreement under delegation F2. The total value to the
Contract Payments
Contract Variations
Table 2 Example of Contract Variations and Payments:
Details
Correct Delegate and Limit
In the second year of the contract the
The third year payment must be approved by the Chief Operating Officer (COO), as the DIFS limit of ≤$500,000 is less than the new total cost to the
Authorised Officers
View Current
This is the current version of this document. To view historic versions, click the link in the document's navigation bar.
The Council has approved the University to participate in an Australian Research Council collaborative research program to undertake clean energy research . Six other Australian universities are parties to the program, and the University of Sydney is the lead organisation who will receive the grant monies. The University of Newcastle is not a party to the Head Agreement. The Head Agreement value is $7,500,000.
The University of Newcastle is a party to a sub-agreement to the Head Agreement. The total value of the sub-agreement is $899,000. The sub-agreement relates to a portion of the grant monies that will be distributed to the University of Newcastle to undertake research elements of the program.
The University is wishing to participate in a research program with an industry partner to conduct research into an emerging area of chemical engineering. Two other Australian universities are parties to the research program. The University of Newcastle is a party to the Head Agreement. The Head Agreement value is $1,500,000.
The University is also a party to a sub-agreement for the development of a testing protocol for the research . The total value of the sub-agreement is $245,000.
The University wishes to enter into a contract for the supply of cleaning services at a cost of $250,000 per year, over a 2 year period. The total cost to the University for the contract is calculated as:
$250,000 x 2 = $500,000.
The contract can be approved by the Director, Infrastructure and Facilities Services (DIFS). The DIFS limit is equal to the total cost of the contract to the University, ≤$500,000.
At this stage, the DIFS can also approve the annual payments of $250,000 to the vendor.
$250,000 x 3 = $750,000.
The contract variation must be approved by the Chief Operating Officer (COO) as the DIFS limit is less than the new total contract cost. The COO limit is ≤$2,000,000.
The second year payment of $250,000 can be approved by the DIFS under their authority and limit of ≤$500,000.
In the third year of the contract, an invoice for the final year payment is issued to the University for $256,000, as the contract allows CPI increases. The total cost to the University for the contract is now calculated as:
$250,000 x 2 = $500,000 + $256,000 = $756,000.