Delegation of Authority Guidelines
Section 1 - Purpose
(1) These Guidelines have been developed to support delegates in executing delegated authorities. This document should be read in conjunction with the Delegation of Authority Framework and its associated higher level documents.
(2) The Delegation of Authority Framework should be referenced for context specific definitions.
Top of PageSection 2 - Guidelines
General
(3) Nothing in this guideline authorises a delegate to do anything which is, or is likely to be, a breach of an approved code of conduct of the
(4) Any matter considered to be a delegation of authority that is not included in the Delegation Schedules should be referred to the most senior position within the
Due Diligence
(5) A delegate should consider the wider impact of a potential decision before making a commitment, including but not limited to:
- the potential effect on other
University areas of operation; - the resources and capability required to meet and provide oversight of any obligation;
- the potential for inadvertently creating a more significant obligation than intended;
- the place of that decision in the scope of emerging technologies;
- if an actual or perceived conflict of interest may exist;
- would the decision seem reasonable if it were reported on a newspaper front page?
- for contractual commitments:
- compliance with relevant legislation and
University policies, including but not limited to the Procurement Policy and Intellectual Property Policy, and their associated documents; - determining if the assignment of
intellectual property and/or licenses is appropriate and within the delegate’s authority; - ensuring the contract is appropriately documented;
- the expenditure is warranted and for a valid
University purpose, and correct as to its amount; and - the other party’s legal status, reputation, and solvency.
- compliance with relevant legislation and
Financial Transaction Limits
(6) A financial limit to a delegation of authority for incurring expenditure:
- relates to the total cost of the transaction to the
University even if paid in instalments, including:- taxes other than GST;
- duties or other associated liabilities; and
- applies to the original cost price of an item not the net cost after deductions of any trade-in or the like; and
- includes any agreed variations to the original cost price.
Contracts and Agreements
Collaborative Agreements – Head and Sub Agreements
Table 1 – Example of Collaborative Head and Sub Agreements
(7) Nothing in the below example should be taken to interpret an actual Head Agreement or Sub-Agreement, and reference should always be made to the current Schedule, available in the Delegations Register.
Example | Correct Delegate and Limit |
---|---|
The Council has approved the
The University of Newcastle is a party to a sub-agreement to the Head Agreement. The total value of the sub-agreement is $899,000. The sub-agreement relates to a portion of the grant monies that will be distributed to the University of Newcastle to undertake |
The Director, Research Grants can execute the sub-agreement under delegation F1. The Director, Research Grants has an unlimited authority for ARC agreements. |
The
The |
The Deputy Vice-Chancellor (Research and Innovation) must execute the Head Agreement and the Sub-Agreement under delegation F2. The total value to the |
Contract Payments
(8) Where a delegated authority exists to approve a contract for a funding commitment; and a separate delegated authority exists to authorise expenditure related to that contract, separate delegates may exercise each individual delegation of authority providing:
- the Delegations of Authority Framework and its associated documents are complied with;
- the limits and conditions of each delegated authority are complied with in relation to the exercise of the individual delegated authority; and
- the exercise of individual authorities does not breach the relevant contract.
Contract Variations
(9) To determine who can approve a contract variation, the limits of the relevant delegated authority should be applied to the sum of the original contract cost, plus the cost of all variations. This applies to all types of contracts, regardless of the relevant authority. (For example, this applies equally to contracts for supply of capital items, contractor services, agency hire staff, operational supplies, etc).
Table 2 Example of Contract Variations and Payments:
Details | Correct Delegate and Limit |
---|---|
The
$250,000 x 2 = $500,000. |
The contract can be approved by the Director, Infrastructure and Facilities Services (DIFS). The DIFS limit is equal to the total cost of the contract to the University, ≤$500,000.
At this stage, the DIFS can also approve the annual payments of $250,000 to the vendor. |
In the second year of the contract the $250,000 x 3 = $750,000. |
The contract variation must be approved by the Chief Operating Officer (COO) as the DIFS limit is less than the new total contract cost. The COO limit is ≤$2,000,000.
The second year payment of $250,000 can be approved by the DIFS under their authority and limit of ≤$500,000. |
In the third year of the contract, an invoice for the final year payment is issued to the
$250,000 x 2 = $500,000 + $256,000 = $756,000. |
The third year payment must be approved by the Chief Operating Officer (COO), as the DIFS limit of ≤$500,000 is less than the new total cost to the |
Authorised Officers
(10) Where the signature of a delegate is required, the Authorised Person must write the words "For and on behalf of (the Role title) as an Authorised Person", so it is clear that the person is acting under the authority of the Delegate.